Phase 3 of the Picton Main Street reconstruction project has concluded for 2025, and the road has reopened to two-lane traffic with no signals. RW Tomlinson Limited completed sanitary and storm sewer work on the west side of the road from #454 County Road 49 to Fawcett Avenue.
A temporary asphalt layer has been installed to allow safe travel during the winter months. The surface will be maintained until a new roadway is installed when the entire project is finished.
Construction will resume in spring 2026 and continue until December 2026. Work will include sewer and watermain replacement, as well as installation of a new roadway, curbs, sidewalks, and street lighting from #454 County Road 49 to Folkard Lane. One lane of traffic will be maintained, and alternate routes will be identified.
Written by Emily Chatwood