Due to poor weather today (December 6) the extended full closure of the Bay of Quinte Skyway Bridge will be taking place next weekend. Initially it was scheduled for this weekend but the Superintendent on the project says it has been delayed. This work is being done in order to complete the final concrete placement to connect the two new decks together prior to final paving. Due to unpredictable temperatures this time of year the concrete needs up to 48 hours to set.
The extended closure has been rescheduled to run from 6 am on Saturday, December 14 until 6 am on Monday, December 16.
If you are unsure about alternate routes, please visit the Glenora Ferry website.